PRILL TOWER, YARA PORSGRUNN

Prill tower

Yara Porsgrunn

Assignment

  • Survey of prill tower, concour, rail.


  • Survey of new foundations with cast in bolts.



  • Survey of the new prefabricated prill tower bottom.


Challenge

  • Prefabricated prill tower bottom = 120 Tons of steel.


  • 14 days stop.


  • Disassembled into 8 pieces for assembly.



  • Could existing documentation be trusted?


Solution

  • Delivery of report for placing the new prill tower bottom with the exact clearances.


  • Production of drawing documenting the new bolt placement on the foundation.



  • Work completed 2 days ahead of schedule.